A and B together take 6 days to complete a task. B and C together take 12 days to complete the same task. A and C together take 8 days to complete it. If A, B and C are working together, how long does it take for them to complete the task?

  • A.4(2/3) days
  • B.4 days
  • C.5(1/3) days
  • D.1(1/3) days