One major difference between PERT (project evaluation and review technique) and CPM (critical path method) is that:

  • A.PERT employs 3 time estimates and CPM employs 4 time estimates
  • B.PERT employs 3 time estimates and CPM employs only 1 time estimate
  • C.PERT employs 1 time estimate and CPM employs 3 time estimates
  • D.None of these